Contract 78040 REL 78: 1987-127-00 EXP SMOLT MONITORING BY PSMFC FY25
Project Number:
Title:
Smolt Monitoring by Non-Federal Entities
Stage:
Implementation
Area:
Province Subbasin %
Basinwide - 100.00%
Contract Number:
78040 REL 78
Contract Title:
1987-127-00 EXP SMOLT MONITORING BY PSMFC FY25
Contract Continuation:
Previous: Next:
78040 REL 67: 1987-127-00 EXP SMOLT MONITORING BY NON-FEDERAL ENTITIES
Contract Status:
Issued
Contract Description:
The smolt-monitoring program (SMP) provides data on movement of salmonid smolts past the series of dams on the Snake and Columbia rivers. Indices of migration timing are provided for the run-at-large at key monitoring sites. In addition, marked smolts from hatcheries provide measures of smolt speed and in-river survival through key reaches. Fish quality, descaling, and gas bubble trauma measures are taken on samples of fish collected at the monitoring sites to provide an indicator of health of the run.

These data are used for in-season operational discussions relative to flow and spill management, particularly during periods when spill is being provided to improve smolt passage at dams.

Non-Salmonid GBT monitoring will continue in the summer at the Bonneville and McNary monitoring facilities.
Account Type(s):
Expense
Contract Start Date:
03/01/2025
Contract End Date:
02/28/2026
Current Contract Value:
$1,514,459
Expenditures:
$116,081

* Expenditures data includes accruals and are based on data through 31-Mar-2025.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
MarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarker
30 km
20 mi
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Catherine Al-Sheikhly Pacific States Marine Fisheries Commission No Interested Party kalsheikhly@psmfc.org (503) 595-3224
Michael Arredondo Pacific States Marine Fisheries Commission No Interested Party marredondo@psmfc.org (503) 595-3100
Paula Calvert Bonneville Power Administration No Interested Party ppcalvert@bpa.gov (503) 230-5651
Ngu Castro Pacific States Marine Fisheries Commission No Administrative Contact ncastro@psmfc.org (503) 595-3229
Michele DeHart Fish Passage Center Yes Supervisor mdehart@fpc.org (503) 833-3901
Israel Duran Bonneville Power Administration Yes Env. Compliance Lead induran@bpa.gov (503) 230-3967
Rodrigo George Bonneville Power Administration Yes F&W Approver rdgeorge@bpa.gov (503) 230-3260x3260
Benjamin Hausmann Bonneville Power Administration No Interested Party bjhausmann@bpa.gov (503) 230-5732
Pam Kahut Pacific States Marine Fisheries Commission No Administrative Contact pam_kahut@psmfc.org (503) 595-3100
Nancy Leonard Pacific States Marine Fisheries Commission Yes Supervisor nleonard@psmfc.org (503) 595-3100
Allan Martin Pacific States Marine Fisheries Commission Yes Contract Manager dmartin@psmfc.org (503) 595-3108
Chris McCarty Fish Passage Center Yes Interested Party cmccarty@fpc.org (503) 833-3900
Jonathan McCloud Bonneville Power Administration Yes COR jmmccloud@bpa.gov (503) 230-3110
Khanida Mote Bonneville Power Administration Yes Contracting Officer kpmote@bpa.gov (503) 230-4599
Lindsey O'Halloran Pacific States Marine Fisheries Commission Yes Contract Manager lo'halloran@psmfc.org (503) 833-3900
Jessica Power Bonneville Power Administration Yes CO Assistant jdpower@bpa.gov (503) 230-4023


Viewing 18 of 18 Work Statement Elements
Sort Order
WSEV ID
WE ID
Work Element Name
Title
Description
WSE Effective Budget
% of Total WSE Effective Budget
WSE Start
WSE End
A251008185Produce CBFish Status ReportPeriodic Status Reports for BPAThe Fish Passage Center Contractor shall report on the status of milestones and deliverables in CBFish. Reports shall be completed monthly, quarterly, or as negotiated with the BPA COR. In each report, when the work reaches a terminal status, additional data (actual metrics, updated budgets, final locations, etc.) may be required upon submitting the report to the BPA COR.$00.00%07/01/202502/28/2026
B251009165Produce Environmental Compliance DocumentationObtain NEPA / Environmental ClearanceEnvironmental Clearance/ESA Compliance$00.00%03/01/202502/28/2026
C251010119Manage and Administer ProjectsPSMFC-SMP Administration of ContractFinancial transactions and reporting for SMP administration and contract. MOAs with subcontractors ODFW, WDFW, and IDFG. Personnel administration of PSMFC personnel involved in the contract.$73,9314.88%03/01/202502/28/2026
D251011119Manage and Administer ProjectsODFW-Little Goose Dam Administration of ContractPlan and prepare for the Smolt Monitoring Program at Little Goose Dam. Prepare new statement of work and budget and submit to FPC by 10/31. Submit invoices to PSMFC for payment.$75,9945.02%03/01/202502/28/2026
E251012157Collect/Generate/Validate Field and Lab DataODFW-Little Goose Dam Smolt MonitoringConduct Smolt Monitoring Program (SMP) activities at Little Goose Dam.$239,98115.85%03/01/202502/28/2026
F251013157Collect/Generate/Validate Field and Lab DataODFW - Gas Bubble Trauma (GBT) at Little Goose DamConduct microscopic exams on Chinook salmon and steelhead looking for symptoms of Gas Bubble Trauma (GBT) at Little Goose Dam April through August, according to regionally agreed scheduled protocols.$20,6911.37%03/01/202502/28/2026
G251014186Operate and Maintain Habitat/Passage/StructureODFW-Fish Ladder Inspections at Little Goose and Lower Granite DamConduct adult fish ladder inspections at Little Goose and Lower Granite Dams.$14,2200.94%03/01/202511/30/2025
H251015119Manage and Administer ProjectsPSMFC-Bonneville Dam Administration of ContractPlan for the Smolt Monitoring activities at Bonneville . Prepare 2026 work statement and budget and submit to FPC by 2/1/2026. PSMFC HQ staffs coordinates the development of budgets for PSMFC contracted projects, at Bonneville, McNary and Lower Granite dams for implementation of the co-managers agreed plans and priorities for the SMP. These budgets are provided to the FPC.$33,0142.18%03/01/202502/28/2026
I251016157Collect/Generate/Validate Field and Lab DataPSMFC-Bonneville Dam Smolt MonitoringImplement smolt monitoring program (SMP) work plan and start sampling at Hamilton Island Juvenile Monitoring Facility (JMF) at Bonneville Dam March - October. Bonneville Dam-Hamilton Island JMF: The JMF, which samples fish from the second powerhouse, will be the primary sampling site at Bonneville. Fish Passage Indices will be calculated from the samples according to FPC established procedures. The facility is equipped with a 3-way rotating gate used for collecting research fish using the SbyC system and diverting them into one of two tanks. On the center flume, or bypass flume, downstream of the 3-way gate, there is a 2-way gate that collects the timed subsample for smolt monitoring. Two to six subsamples are collected per hour, 24 hours per day and processed first at 0700, and possibly again at midday, depending on conditions and fish numbers. Sample rates are adjusted to collect about 500 fish per day in the spring and 250 fish per day in the fall. Personnel will be on site 24 hours per day to monitor dewatering screens and holding tanks, and fish distribution flumes.$215,32514.22%03/01/202502/28/2026
J251017157Collect/Generate/Validate Field and Lab DataPSMFC-Gas Bubble Trauma (GBT) at Bonneville DamConduct microscopic exams on Chinook salmon, steelhead and non-salmonids looking for symptoms of Gas Bubble Trauma (GBT) at the Hamilton Island Juvenile Facility, Bonneville Dam April through August.$35,0962.32%03/01/202502/28/2026
K251018186Operate and Maintain Habitat/Passage/StructurePSMFC-Monitor Bonneville Separator and Clear when NecessaryMonitor the separators at all Bonneville Dam 24 hours/day and clear when necessary.$164,36310.85%03/01/202511/30/2025
L251019119Manage and Administer ProjectsWDFW/PSMFC- LGR & MCN Dams Administration of ContractPlan and oversee smolt monitoring program at LGR and MCN. Submit invoices to PSMFC. Provide financial and project information to FPC & PSMFC as requested and required by the SMP contract. Prepare the 2026 SOW and budget and submit to FPC by 11/1/2025.$107,7427.11%03/01/202502/28/2026
M251020157Collect/Generate/Validate Field and Lab DataWDFW/PSMFC- LGR Dam Smolt MonitoringCollect, record, summarize, and verify all sample data daily. Collect, record and verify daily USACE project operations and flow data, fish transport numbers, and facility fish mortalities.$207,41013.70%03/01/202502/28/2026
N251021157Collect/Generate/Validate Field and Lab DataWDFW/PSMFC- Gas Bubble Trauma (GBT) at LGR DamConduct microscopic exams looking for symptoms of Gas Bubble Trauma (GBT) at the Juvenile Facility at LGR April through June. According to agreed upon protocol and schedule.$33,0922.19%03/01/202502/28/2026
O251022157Collect/Generate/Validate Field and Lab DataWDFW/PSMFC- MCN Dam Smolt MonitoringCollect, record, summarize, and verify all sample data daily. Collect, record and verify daily USACE project operations and flow data, fish transport numbers, and facility fish mortalities. On every other day provide sample Fish to PNNL Yesresearchs for use in the federal agencies acoustic tag study from March 26 and end on June 7$230,63215.23%03/01/202502/28/2026
P251023157Collect/Generate/Validate Field and Lab DataWDFW/PSMFC- Gas Bubble Trauma (GBT) at MCN DamConduct microscopic exams on Chinook, steelhead and non-salmonids looking for symptoms of Gas Bubble Trauma (GBT) at the McNary Juvenile Facility from April through August according to agreed upon regional protocols and schedules- available at FPC.$42,2772.79%03/01/202502/28/2026
Q251024157Collect/Generate/Validate Field and Lab DataODFW - Gas Bubble Trauma (GBT) at LMN DamConduct microscopic exams looking for symptoms of Gas Bubble Trauma (GBT) at the Lower Monumental Juvenile Facility from April through August.$20,6911.37%03/01/202502/28/2026
      
$1,514,459
   

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental Clearance B: 165. Obtain NEPA / Environmental Clearance 02/28/2026
Effective implementation management and timely contract administration C: 119. PSMFC-SMP Administration of Contract 02/28/2026
Effective implementation management and timely contract administration D: 119. ODFW-Little Goose Dam Administration of Contract 02/28/2026
Produce accessible, error-checked datasets E: 157. ODFW-Little Goose Dam Smolt Monitoring 02/28/2026
Produce accessible, error-checked datasets F: 157. ODFW - Gas Bubble Trauma (GBT) at Little Goose Dam 02/28/2026
Functioning Fish Ladders G: 186. ODFW-Fish Ladder Inspections at Little Goose and Lower Granite Dam 11/30/2025
Effective implementation management and timely contract administration H: 119. PSMFC-Bonneville Dam Administration of Contract 02/28/2026
Produce accessible, error-checked datasets I: 157. PSMFC-Bonneville Dam Smolt Monitoring 02/28/2026
Produce accessible, error-checked datasets J: 157. PSMFC-Gas Bubble Trauma (GBT) at Bonneville Dam 02/28/2026
Monitor the separator K: 186. PSMFC-Monitor Bonneville Separator and Clear when Necessary 11/30/2025
Effective implementation management and timely contract administration L: 119. WDFW/PSMFC- LGR & MCN Dams Administration of Contract 02/28/2026
Produce accessible, error-checked datasets M: 157. WDFW/PSMFC- LGR Dam Smolt Monitoring 02/28/2026
Produce accessible, error-checked datasets N: 157. WDFW/PSMFC- Gas Bubble Trauma (GBT) at LGR Dam 02/28/2026
Produce accessible, error-checked datasets O: 157. WDFW/PSMFC- MCN Dam Smolt Monitoring 02/28/2026
Produce accessible, error-checked datasets P: 157. WDFW/PSMFC- Gas Bubble Trauma (GBT) at MCN Dam 02/28/2026
Produce accessible, error-checked datasets Q: 157. ODFW - Gas Bubble Trauma (GBT) at LMN Dam 02/28/2026
Completed Progress (Annual) Report R: 132. Submit Progress Report for SMP activities to the FPC for the period (03/01/2025) to (02/29/2026) 08/31/2025

Viewing of Implementation Metrics
Loading...
Sort Order
WE ID
Work Element Name
Title
Description
Metric ID
Metric
End Fiscal Year
Planned
Actual
Contractor Comments
All Measures
Annual Progress Report Measures
Populations
Viewing of Environmental Metrics Customize
Loading...
WSE ID
WSE Start
WSE End
WE ID
Title
WSE Progress
Study Plan
Protocol
Category
Subcategory
Focus 1
Focus 2
Specific Metric Title

Primary Focal Species Work Statement Elements
Chinook (Oncorhynchus tshawytscha) - All Populations
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 9 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Coho (Oncorhynchus kisutch) - Lower Columbia River ESU (Threatened)
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Coho (O. kisutch) - Unspecified Population
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Sockeye (Oncorhynchus nerka) - All Populations
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Steelhead (Oncorhynchus mykiss) - All Populations
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 9 instances of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 165 Obtain NEPA / Environmental Clearance
C 119 PSMFC-SMP Administration of Contract
D 119 ODFW-Little Goose Dam Administration of Contract
E 157 ODFW-Little Goose Dam Smolt Monitoring
F 157 ODFW - Gas Bubble Trauma (GBT) at Little Goose Dam
G 186 ODFW-Fish Ladder Inspections at Little Goose and Lower Granite Dam
H 119 PSMFC-Bonneville Dam Administration of Contract
I 157 PSMFC-Bonneville Dam Smolt Monitoring
J 157 PSMFC-Gas Bubble Trauma (GBT) at Bonneville Dam
K 186 PSMFC-Monitor Bonneville Separator and Clear when Necessary
L 119 WDFW/PSMFC- LGR & MCN Dams Administration of Contract
M 157 WDFW/PSMFC- LGR Dam Smolt Monitoring
N 157 WDFW/PSMFC- Gas Bubble Trauma (GBT) at LGR Dam
O 157 WDFW/PSMFC- MCN Dam Smolt Monitoring
P 157 WDFW/PSMFC- Gas Bubble Trauma (GBT) at MCN Dam
Q 157 ODFW - Gas Bubble Trauma (GBT) at LMN Dam
R 132 Submit Progress Report for SMP activities to the FPC for the period (03/01/2025) to (02/29/2026)